Implementation ProcessImplementation Step 8: Develop a Plan of ActionGeneral DescriptionAt this stage, the working group will usually detail the program which has been selected for implementation. This step translates the program into an action plan, with all the details needed by both decision-makers, who will have to commit to the investment of resources, and those charged with carrying it out. The effort involves defining resource requirements, organizational and institutional arrangements needed, schedules, etc. This is usually done in the form of what may be called a "business plan," or plan of action. An example of a plan developed by a local community is shown in Appendix X. An evaluation plan should be designed at this point. It is an important part of the plan. This is something that should be in place before Step 9 is finished. It is not acceptable to wait until after the program is completed to begin designing an evaluation of it. This is because data are needed about conditions before the program starts, to allow comparison with conditions during its operation and after its completion. It also should be designed at this point, to achieve consensus among the stakeholders on what constitutes "success." The evaluation is used to determine just how well things were carried out and what effect the program had. Knowing this, helps maintain the validity of what is being done, encourages future support from management, and provides good intelligence on how to proceed after the program is completed. For further details on performing evaluations, see Appendix L, Appendix M, and Appendix W. The plan of action should be developed jointly with the involvement of all desired participants in the program. It should be completed to the detail necessary to receive formal approval of each agency during the next step. The degree of detail and complexity required for this step will be a function of the size and scope of the program, as well as the number of independent agencies involved. Specific Elements
|