Horizontal Curves

Index of Strategies by Implementation Timeframe and Relative Cost

Exhibit IV-1 provides a classification of strategies according to the expected timeframe and relative cost for this emphasis area. In several cases, the implementation time will depend on such factors as the agency’s procedures, the need for additional right-of-way (ROW), and the need to follow environmental impact processes. The range of costs also may vary for some of these strategies depending on many of the same factors. Placement in the exhibit is meant to reflect the most commonly expected application of the strategy.

EXHIBIT IV-1
Strategies Classified by Relative Cost and Time Necessary for Implementation

Relative Cost to Implement and Operate

Strategy

Time Frame: Short (less than a year)

Low

15.2 A1 Provide advance warning of unexpected changes in horizontal alignment

15.2 A2 Enhance delineation along the curve

15.2 A3 Provide adequate sight distancea

15.2 A4 Install shoulder rumble strips

15.2 A5 Install centerline rumble strips

15.2 A6 Prevent edge dropoffsb

15.2 B2 Remove/relocate objects in hazardous locationsc

15.2 B3 Delineation of roadside objects

Moderate

Moderate to High

High

Time Frame: Medium (1–2 years)

Low

Moderate

15.2 A7 Provide skid-resistant pavement surfaces

15.2 A8 Provide grooved pavement

15.2 A9 Provide lighting of the curve

15.2 A10 Provide dynamic curve warning system

Moderate to High

15.2 A15 Prohibit/restrict trucks with very long semitrailers on roads with horizontal curves that cannot accommodate truck offtrackingd

15.2 B4 Add or improve roadside hardware

15.2 B5 Improve design and application of barrier and attenuation systems

15.2 A11 Widen the roadwaye

15.2 A12 Improve or restore superelevation

15.2 A14 Install automated anti-icing systems

15.2 B1 Design safer slopes and ditches to prevent rollovers

High

Time Frame: Long (more than 2 years)

Low

Moderate

Moderate to High

High

15.2 A13 Modify horizontal alignment

aProviding adequate sight distance can be costly if it involves redesigning the vertical curvature of the roadway or cutting back the slope of a hillside. It is assumed here, however, that most sight obstructions will be longitudinal barriers such as trees or foliage that may be cut back at minimal costs.

bThe action could be done in a short timeframe. However, it is assumed to be done at little extra cost as part of a regular repaving program.

cRemoval/relocation of some objects (e.g., bridge abutments and drainage structures) can be costly, depending upon the object. It is assumed here, however, that most objects will be small appurtenances.

dThis strategy is considered medium cost because it may consume a considerable number of staff-hours to develop such a policy and have it approved.

eWidening the roadway does not necessarily require acquisition of additional right-of-way (ROW). If ROW is needed, the cost will be moderate to high, and the time required will be long.