Run-Off-Road Collisions
Index of Strategies by Implementation Timeframe and Relative Cost
Exhibit IV-1 provides a classification of strategies according to the expected timeframe and relative cost for this emphasis area. In several cases, the implementation time will be dependent upon such factors as the agency's procedures, the length of roadway involved, the need for additional right-of-way, and the need to follow environmental impact processes. The range of costs may also vary for some of these strategies because of many of the same factors. Placement in the table below is meant to reflect the most common expected application of the strategy.
EXHIBIT IV-1 Classification of Strategies According to Expected Timeframe and Relative Cost
| |
|
Relative Cost to Implement and Operate |
Timeframe for Implementation |
Strategy |
Low |
Moderate |
Moderate to High |
High |
Short (<1 year) |
15.1 A1Install rumble strips |
 |
|
|
|
| |
15.1 A3Install midlane rumble strips |
 |
|
|
|
| |
15.1 A4Provide enhanced delineation of sharp curves |
 |
|
|
|
| |
15.1 A6Provide enhanced pavement markings |
 |
|
|
|
| |
15.1 B3Remove/relocate objects in hazardous locationsa |
 |
|
|
|
Medium (12 (years) |
15.1 A7Provide skid-resistant pavements |
|
 |
|
|
| |
15.1 A8Eliminate shoulder drop-offb |
 |
|
|
|
| |
15.1 B1Provide shoulder treatmentsc or four-lane sections at key locations* |
|
 |
|
|
| |
15.1 B2Design safer slopes and ditches |
|
|
 |
|
| |
15.1 C1Improve roadside hardware |
|
|
 |
|
| |
15.1 C2Improve barrier and attenuation systems |
|
|
 |
|
Long (>2 years) |
15.1 A5Improve horizontal curve geometryd |
|
|
|
 |
a Removal/relocation of some objects (e.g., bridge abutments and drainage structures) can be costly, depending upon the object. It is assumed here, however, that most objects will be small appurtenances.
b The action could be done in a short timeframe. However, it is assumed to be done at little extra cost as part of a regular repaving program.
c The classification of shoulder treatments and safer slopes and ditches as moderate-cost or moderate-to-high-cost treatments assumes that no additionalright-of-way is needed. If right-of-way is needed, the cost could be high and the time required would be long.
d Although the AASHTO Strategic Highway Safety Plan is focused upon relatively low-cost, short-term strategies, there are some higher-cost strategies such as curve flattening that have potential for such significant effectiveness that they have been included. Curve flattening would primarily be applicable in rehabilitation, resurfacing, and restoration (3R) and reconstruction projects that have been programmed outside the context of the AASHTO plan initiative.
|
|